Skip to main content

menu
Highland Hospital / Facilities / Blog / April 2021 / Ramp Demolition On Hold

Ramp Demolition On Hold

The demolition of the ramp slab has been temporarily halted. Once demolition resumes, there will be approximately two more weeks of demolition.

Micropile installation will resume at the end of April and will continue for approximately three weeks. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 4/22/2021

You may also like

No related posts found.