Skip to main content

menu
Tower Crane Removal Update

Tower Crane Removal Update

Mt. Vernon Ave. is now closed to through traffic with all detours posted. Tower Crane disassembly has begun. Unfortunately, due to the wind speed and the impending snow event on Friday, all tower crane work has been suspended until Monday morning. Constructors will be plowing and salting Mt. Vernon from Rockingham St. to the crane and Doctors Dr./Bellevue Drive to the crane over the weekend.  Safety is our number one priority: for our neighbors, the hospital, and our construction workers.

Once work resumes next week, there will be tractor trailers on Mt. Vernon loading out crane components similar to when the crane was set up. 

Site access will need to vary depending on the disassembly crane location; when the disassembly crane is on Mt. Vernon access will be from the South Avenue side. When the disassembly crane is on site, access will be from Mt. Vernon through our current entrance for safety.

Tower Crane Removal

Tower Crane Removal

Mt. Vernon is now closed to through traffic with all detours posted. Unfortunately, due to weather, the disassembly crane will not be able to be set up until Saturday. Contractors are currently trying to thaw out both cranes and the roadway. There will be tractor trailer set up on Mt. Vernon loading out crane components, similar to when the crane was set up.

Site access for construction will need to vary depending on the disassembly crane location. When the disassembly crane is on Mt. Vernon, access will be from South Avenue side. When the disassembly crane is on site, access will be from Mt. Vernon for safety.

Crews will be on site this Saturday 2/25 from 7 a.m. to 5 p.m. installing panels and possibly disassembling the tower crane, depending on weather.

During the week, crews continue to finish drywall and mechanical installations inside the building. Outside, window, exterior siding, and roofing installation continues on various elevations.

Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Tower Crane Removal and Saturday Work

Tower Crane Removal and Saturday Work

The tower crane will be disassembled during the weeks of February 20 and 27.  Mt. Vernon Ave. will be closed to non-resident traffic starting Thursday, February 23 to set up the crane used to disassemble the big crane and remain closed through the weekend, into the week of February 27. Extensive signage will be placed to inform drivers of the closure and alternate routes, following all City of Rochester regulations for road closure. Weekend disassembly work will also take place on Saturday, February 25 only. 

Mt. Vernon Closure Dates and Saturday Work

Mt. Vernon Closure Dates and Saturday Work

The tower crane will be coming down the weeks of February 20 and 27.  Mt. Vernon Ave. will be closed to non-resident traffic starting Thursday, February 23 to set up the crane used to disassemble the big crane and remain closed through the weekend, into the week of February 27. Extensive signage will be placed to inform drivers of the closure and alternate routes, following all City of Rochester regulations for road closure. Weekend disassembly work will also take place on Saturday, February 25 only. 

Saturday Work 2/4

Saturday Work 2/4

Crews will be onsite Saturday 2/4 from 7 a.m. to 5 p.m. installing fiber cement panels (weather depending).

During the week, crews continue to paint, and install various mechanicals inside the building. Outside, crews will be using the tower crane to move materials from the ground to various floors of the building. They will also be working on window and siding installation as well as roofing on the 7th floor and bump outs.