Crews continue saw cutting and removing the remaining portion of the ramp slab and foundations. This will continue for two more weeks.
Micropile installation will resume at the end of April and will continue for approximately three weeks. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation.
Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.