Skip to main content

menu
Highland Hospital / Facilities / Blog / August 2022 / Saturday Work 8/20

Saturday Work 8/20

Crews will be on site Saturday 8/20 from 7 a.m. to 5 p.m. Carpenters will be working on drywall and miscellaneous framing while mechanicals and piping are installed on the upper floors. Various exterior work will also be done using the swing stage scaffolding.

During the week, crews will be using the tower crane and buck hoist for activities on site. Fire proofing continues from scaffolding outside the structure. Interior and exterior framing will be installed on the 5th, 6th, 7th, and mechanical penthouse floors. Drywall top fill is being completed on the 6th and 7th floors for mechanicals and drywall finishing is happening on all of the floors. Mechanical, electrical, and plumbing rough ins continue throughout the addition. Brick is being installed on the fuel oil building and new exit corridor.

Next week there will be deliveries at the South Ave. entrance to the hospital from Tuesday 8/23 to Thursday 8/25 that may mean other simultaneous deliveries need to be redirected to the Mt. Vernon entrance.  If this happens, flaggers will be on site to direct traffic flow.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency. 

Wendy Boyce | 8/18/2022

You may also like

No related posts found.