Skip to main content

menu
Highland Hospital / Facilities / Blog / August 2022 / Saturday Work 8/27 and Generator Testing

Saturday Work 8/27 and Generator Testing

Crews will be on site this Saturday 8/27 from 7 a.m. to 5 p.m. Carpenters will be working on drywall. Mechanical and piping installations will also be taking place inside the building. Outside, miscellaneous exterior work will continue from the scaffolding.

The annual code required generator testing will also be occurring on Saturday from 7 a.m. to noon. The testing will sound like a truck motor running.

During the week, crews will be using the tower crane and buck hoist for activities on site. Fire proofing continues on structural members from the scaffolding. Crews will be installing the interior and exterior framing on the 5th, 6th, 7th, and mechanical floors. Drywall top fill will be installed on the 6th and 7th floor for mechanicals and mechanical, electrical, and plumbing rough ins continue throughout the building.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency. 

Wendy Boyce | 8/25/2022

You may also like

No related posts found.