Second Fuel Tank Installed

The second fuel tank has been delivered.  Backfilling and shoring removal for the tank is scheduled to begin on Monday, December 21. This is expected to cause the same level of noise as the shoring of the first tank.

Construction of the Pump House is scheduled to begin next week after the second tank is fully installed. The pump house will be attached to the hospital, behind the area of the first tank. Construction will start with drilling a micropile and building the foundations. 

No work is scheduled for December 25, 26, 27 or January 1, 2, and 3.  Crews will be working no later than 3:30 p.m. on Christmas Eve and New Year’s Eve.

Global Administrator | 12/17/2020