Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / December 2021 / Saturday Work 12/11

Saturday Work 12/11

Crews will be onsite this Saturday for structural steel erection and decking detailing from 7 a.m. to 4 p.m., depending on the weather.

During the week, the tower crane will be in operation with the super structure steel as the steel workers will be detailing decking. Mechanical hangers will also be installed on the new decks of the 2nd,  3rd, 4th and 5th floors for future installation of the mechanical piping. Crews will also be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, and embedment’s. This includes drilling into the east side second and third floor concrete slabs.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 12/9/2021

You may also like

No related posts found.