Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / December 2021 / Saturday Work 12/18

Saturday Work 12/18

Crews will be on site this Saturday 12/18 continuing with structural steel erection and detailing decking from 7 a.m. to 4 p.m. (weather dependent).

The construction site will be shut down Friday 12/24 for the Christmas Holiday and Friday 12/31 for the New Year’s Holiday.  No work will occur over the holiday weekends. 

During the week next week, the tower crane will be in operation assembling the super structure steel as steel workers detail the decking. Mechanical hangers will be put in on the 2nd,  3rd, 4th, 5th and 6th floors new decks for future installation of the mechanical piping. Crews will also be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, embedment’s and rebar. The stair risers are being filled with concrete for easier access from floor to floor.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 12/16/2021

You may also like

No related posts found.