Skip to main content

menu
Highland Hospital / Facilities / Blog / February 2021 / Tower Crane Foundation Installation

Tower Crane Foundation Installation

Installation of reinforcing for the Tower Crane foundation is underway. A small crane will be setting the anchors for the Tower Crane, then construction of the concrete pad will follow.

Fuel Pump Room concrete work is underway along the south side of the existing South Addition. Crews continue with forming, installing reinforcing and placing concrete at these locations.

Excavation and installation of the underground fuel lines from the tanks to the Fuel Oil Pump Room are underway and anticipated to continue through next week.

All of these activities are expected to create typical levels of construction noise and truck traffic.

Wendy Boyce | 2/18/2021

You may also like

No related posts found.