MRI Replacement Project & North Retaining Wall Update
MRI Replacement Project
The MRI Replacement Project, which began in September, is on schedule. The new MRI will be delivered on Friday, Jan. 24. On that day, Bellevue Drive will be closed to traffic east of the construction trailers heading toward the hospital’s discharge area. The alley off of Bellevue Drive and entrance to the hospital will accessible to traffic. The temporary wooden staircase on Bellevue Drive will be removed on Jan. 28 or 29 and the window will be reinstalled.
North Retaining Wall Update
The North Wall Project continues to move forward. To maintain the integrity of the wall, additional supports have been designed. The material to complete these supports is on order and expected by mid-to-late February.
1/17/2020
You may also like
No related posts found.