Crews will be doing foundation drilling work on Saturday, July 10 from 7 a.m. to 5 p.m. in the temporary canyon area between the current south wing and the south addition.

Deep foundation, pile cap and grade beam installation is ongoing and will continue for approximately 7 weeks. Excavation and grading work are happening at the same time as the deep foundation installations.

South Building roofing work has been delayed but will continue shortly.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.