Skip to main content

menu
Highland Hospital / Facilities / Blog / July 2022 / Saturday Work 7/16

Saturday Work 7/16

Crews will be on site Saturday 7 a.m. to 5 p.m. working on fire proofing and installing mechanicals inside the building. They will also be working on miscellaneous exterior work from the scaffolding outside the building.

During the week, the tower crane and buck hoist will be used for activities on site. Crews will be continuing to fire proof inside the structure and installing the interior and exterior framing throughout the building. Drywall top fill will be installed on the 5th, 6th, and 7th floors and mechanical rough ins are being put in throughout the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Contractors will also be on site Tuesday 7/19, Wednesday 7/20, and Thursday 7/21 to replace a manhole cover in the hospital’s driveway between the North Lot and the hospital building near the North entrance. This work will be done between the hours of 7 a.m. to 4 p.m. and may include jackhammering sounds. Traffic at this entrance should not be impacted by this work.

Wendy Boyce | 7/14/2022

You may also like

No related posts found.