Skip to main content

menu
Highland Hospital / Facilities / Blog / July 2022 / Saturday Work 7/9

Saturday Work 7/9

Crews will be on site Saturday 7/9 from 7 a.m. to 5 p.m. working on fire proofing structural members within the building and installing water-resistive barriers on the east side outside the building.

During the week, crews will be using the tower crane and buck hoist for activities on site. Interior and exterior framing will be happening on the 5th, 6th, 7th and mechanical penthouse floors. Workers will be using boom lifts to install the framing, sheathing, and water-resistive barriers. They will also be installing drywall top fill on the 5th, 6th, and 7th floors as well as mechanical, electrical, and plumbing rough ins throughout the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 7/7/2022

You may also like

No related posts found.