Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / June 2022 / Saturday Work 6/18

Saturday Work 6/18

Crews will be on site this Saturday, 6/18 from 7 a.m. to 5 p.m. doing fire proofing and installing plumbing inside the building. Exterior framing and sheathing will also be in the process of being installed on the outside of the building.

During the week, crews will be using the tower crane and buck hoist for a variety of construction related activities between 7 a.m. and 6 p.m. Fire proofing structural members will be occurring on the 4th floor for framing. Interior and exterior framing will be happening on the 5th, 6th, 7th and mechanical penthouse levels. Crew members will be working from boom lifts around the building to install framing and sheathing. Drywall will be installed on the 5th, 6th, and 7th floors. Mechanical, electrical and plumbing roughs in are also being put into multiple locations within the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 6/16/2022

You may also like

No related posts found.