Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / March 2022 / No Work This Weekend

No Work This Weekend

There will be no outdoor work on site this weekend Saturday 3/5 or Sunday 3/6.

During the week, crews will be using the crane to install roofing. The 8th floor concrete slab installation is tentatively scheduled for Friday, March 4 starting at 7 a.m. Stair L risers are being filled with concrete for easier access is tentatively scheduled for Thursday, March 10 starting at 7 a.m.  All concrete finishing has the potential to run late into the night but will be finished before the City of Rochester noise ordinance begins at 10 p.m. Layout will begin on the 5th, 6th and 7th floors and top track. Fire Proofing will take place on the 4th, 5th  and 6th floors before framing is installed. Interior and exterior framing will begin on the 1st and 2nd floors.

Please keep in mind that for the stair N risers and the 8th floor concrete pour, crews anticipate having the concrete pump on the South side of the new tower (engine running the during the entire pour), 2 concrete trucks rotating in and out at the concrete pump (engines running), 1 concrete truck washing out (engine running) and one staging on Bellevue Drive (the hospital part of the street) in front of the trailers.  Sometimes due to traffic and how the pour is going, crews may end up with 2 trucks staging on Belleview Drive for a short period of time. Crews will be in constant communication with the batch plant adjusting truck spacing depending on how the pour is progressing.

There will be a flag person at the South Avenue entrance backing in the concrete trucks and prioritizing ambulance access.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 3/3/2022

You may also like

No related posts found.