Saturday Work 3/19
Crews will be on site Saturday, 7 a.m. to 4 p.m. fireproofing the 5th floor of the new tower and installing framing and layout.
During the week, the tower crane will be in operation with roofing and other activities on site. Layout will be going in on the 6th and 7th floor including installation of the top track. Fire Proofing structural members will be happening on the 4th, 5th and 6th floors. Interior and exterior framing will also be happening on the 1st, 2nd and 5th floors. Stairs are being installed between the 3rd and 4th floors and detailing and swing stage scaffolding will be installed on the east side, working its way around to the north side. A Buck Hoist (temporary exterior elevator) will be installed on the South side exterior of the new tower.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Wendy Boyce | 3/17/2022