Skip to main content

menu
Highland Hospital / Facilities / Blog / March 2023 / Saturday Work 4/1

Saturday Work 4/1

Crews will be on site this Saturday 4/1 from 7 a.m. to 5 p.m. working on installing the fiber cement panels and roofing on the outside of the building, weather depending.

During the week, crews are working on hard wall protection, flooring, and various mechanical/electrical finishes throughout the interior. Outside, work continues on the exterior brick work as well as the roofing and siding.

Crews are anticipating bringing the site work up to grade at the end of April to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Wendy Boyce | 3/30/2023

You may also like

No related posts found.