Skip to main content

menu
Highland Hospital / Facilities / Blog / May 2021 / Weekend Ramp Demolition and Roof Work

Weekend Ramp Demolition and Roof Work

Demolition of the ramp slab continues on week days after 1 p.m. until dusk and on weekends starting at 7 a.m. until 5 p.m. Some of this demolition work may require some jack hammering of foundations if they cannot be detached by saw cutting. This work may result in increased noise from the construction site.

Due to the schedule change to the demolition, micropile installation will resume in early June and will continue for approximately 3 week.

South Building roofing work is scheduled to start the week of May 17th and will last approximately 9 weeks. This work will include tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment.  It will require cranes for rigging materials and equipment to the roof.  These will be staged in the Mt. Vernon cut out and will necessitate partial temporary road and sidewalk closures along Mt. Vernon. A flagger will be used during deliveries that could impact travel flow. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 5/13/2021

You may also like

No related posts found.