Crews will be onsite this Saturday 11/20 for structural steel erection and detailing decking from 7 a.m. to 4 p.m., unless there is inclement weather.
During the week, crews will be excavating and grading to install the new natural gas line from Mt. Vernon. This means the sidewalk will be closed on the west side of Mt. Vernon from Monday to Friday next week.
The tower crane will be in limited operation with the super structure steel as the steel workers will be detailing the decking. Mechanical hangers will be installed on the new 2nd and 3rd floor decks for future installation of the mechanical piping. Workers will be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, and embedment’s. This includes drilling into the East side second and third floor concrete slabs. Crews will also begin wrapping the structure temporarily for winter.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.