Skip to main content

menu
Highland Hospital / Facilities / Blog / November 2022 / Saturday Work 11/19

Saturday Work 11/19

Crews will be on site this Saturday 11/19 from 7 a.m. to 5 p.m. installing windows and siding, weather permitting.

During the week, crews will be using the tower crane and buck hoist for various activities on site. Inside, painting, drywall finishing, and various mechanical installations continue on multiple floors. Outside, crews will be installing windows and siding on various sides of the building and continuing to put in the roof on top of the 7th floor.

These activities are expected to produce typical levels of construction noise but no vibrations.

There will be no blog post sent out next week and no work on site Thursday, 11/24, because of the Thanksgiving holiday. Crews will be on site next Friday 11/25 and Saturday 11/26 from 7 a.m. to 5 p.m. painting inside the building and installing windows on various sides.

In early December, crews will be working to raise the pavement area next to the new tower to be the same level as Mt. Vernon Ave. This activity is anticipated to generate some minor vibration, and more details will be sent out via this blog as we get closer to this work occurring.

Wendy Boyce | 11/17/2022

You may also like

No related posts found.