No MRI Construction This Weekend 11/2 and 11/3
There will be no outside work taking place on the MRI over the weekend. On Thursday, October 31, the first delivery of concrete was completed. A second delivery will happen after November 11. The welder will be in use off and on until November 7. The welder produces a low humming noise. Inside the building the contractors will be working on relocating and installing the electrical, plumbing and HVAC.
Wendy Boyce | 10/31/2019