North Retaining Wall
On Monday, October 14, construction will begin on the brick screening wall on the north lot. On Monday and Tuesday, there will be deliveries to the north parking lot of construction materials. On Tuesday and Wednesday scaffolding will be erected on the exit end of the parking lot along the existing retaining wall. Around October 21, installation of the brick clad screening panels will begin. It is expected to be completed by mid-November.
Wendy Boyce | 10/10/2019