Crews will be onsite Saturday 10/15 from 7 a.m. to 5 p.m. Miscellaneous work will be happening from the swing stage scaffolding including hunter panel installation and window installation.
During the week, the tower crane and buck hoist will be used for activities onsite. Full height drywall installation and drywall finishing continues on all floors. Primer and the first coat of paint is going in where drywall is finished. Mechanical, electrical, and plumbing rough ins continue throughout the building. Brick installation on the building is almost 90% complete. Roofing continues on the 7th floor and the mechanical penthouse. Miscellaneous crane picks continue for glass, window frames, etc.
Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.