No Weekend Work 9/18 or 9/19

This week deep foundation, pile cap and grade beam installation will continue and is expected to last through the end of September. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start at the end of September. Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be operating to install the structural steel.

Micro Pile installation is now complete.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 9/16/2021