No Work Labor Day Weekend
There will be no work on the construction site Saturday 9/4, Sunday 9/5, or Monday 9/6 for Labor Day weekend.
The Tower Crane will be in full operation with the start of the super structure steel.
Micro Pile installation has resumed for a week or so to complete the balance of the piles. This will include excavations for the shoring being installed with micro piles.
Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start in mid-September. Fill material will be placed in “lifts” and compacted until the final grade height is reached.
Deep foundation, pile cap and grade beam installation is ongoing and will continue through mid-September. Excavation and grading work will happen at the same time as the deep foundation installations.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Wendy Boyce | 9/2/2021
You may also like
No related posts found.