Skip to main content

menu
Deep Foundation Work Begins

Deep Foundation Work Begins

Micropile installation will be complete this week. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation and will continue for approximately 10 weeks.

Excavation and grading work will happen at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start in late July, early August.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

South Building roofing work is almost complete. This work requires cranes for rigging materials and equipment to the roof.  These are staged along Mt Vernon and necessitate temporary road and sidewalk closures along Mt. Vernon in front of the South Building, including the parking spaces in front of Oncology on Mt. Vernon. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

No Weekend Construction and Micropiles

No Weekend Construction and Micropiles

There will be no construction this weekend on either Saturday June 5 or Sunday June 6.

Micropile installation has started and will continue for approximately 3 weeks. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation (end of June, early July) and will continue for approximately 10 weeks.

Excavation and grading work will happen at the same time as the micro pile and deep foundation installations.

South Building roofing work continues. This work will require cranes for rigging materials and equipment to the roof.  These will be staged along Mt Vernon and will necessitate temporary road and sidewalk closures along Mt. Vernon in front of the South Building, including the parking spaces in front of Oncology on Mt. Vernon. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

No Work Memorial Day Weekend

No Work Memorial Day Weekend

There will be no construction work on site over Memorial Day Weekend.

Recent work on the hospital’s main garage will conclude tonight at 6 p.m. A couple of smaller repairs will take place in a few weeks during daytime hours only and the noise impact of those repairs should be minimal.

Micropile installation will resume on June 1 and will continue for approximately 3 weeks.

South Building roofing work has started and will last approximately 8 weeks. This work will include tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment.  It will require cranes for rigging materials and equipment to the roof.  These will be staged in the Mt. Vernon cut out and will necessitate partial temporary road and sidewalk closures along Mt. Vernon. A flagger will be used during deliveries that could impact travel flow. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Weekend Ramp Demolition Continues

Weekend Ramp Demolition Continues

Demolition of the ramp slab continues on week days after 1 p.m. until dusk and on weekends starting at 7 a.m. until 5 p.m. Some of this demolition work may require some jack hammering of foundations if they cannot be detached by saw cutting. This work may result in increased noise from the construction site.

Micropile installation will resume on June 1 and will continue for approximately 3 weeks.

South Building roofing work has started and will last approximately 9 weeks. This work will include tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment.  It will require cranes for rigging materials and equipment to the roof.  These will be staged in the Mt. Vernon cut out and will necessitate partial temporary road and sidewalk closures along Mt. Vernon. A flagger will be used during deliveries that could impact travel flow. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Weekend Ramp Demolition and Roof Work

Weekend Ramp Demolition and Roof Work

Demolition of the ramp slab continues on week days after 1 p.m. until dusk and on weekends starting at 7 a.m. until 5 p.m. Some of this demolition work may require some jack hammering of foundations if they cannot be detached by saw cutting. This work may result in increased noise from the construction site.

Due to the schedule change to the demolition, micropile installation will resume in early June and will continue for approximately 3 week.

South Building roofing work is scheduled to start the week of May 17th and will last approximately 9 weeks. This work will include tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment.  It will require cranes for rigging materials and equipment to the roof.  These will be staged in the Mt. Vernon cut out and will necessitate partial temporary road and sidewalk closures along Mt. Vernon. A flagger will be used during deliveries that could impact travel flow. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.