Fuel Pump Room and Tower Crane Pad

Fuel Pump Room and Tower Crane Pad

Foundations for the Fuel Pump Room are underway along the south side of the existing South Addition. The Fuel Pump Room is scheduled to be complete by the end of February.

Brick removals on the existing hospital and South Building have resumed and are anticipated to continue for another week. Demolition of the former discharge ramp will also continue for another week or two. 

Excavation and installation of shoring for the tower crane pad (concrete base) will start on Monday, January 18. This is expected to create noise, but not as much as previous shoring as a different type of shoring system is being used. The crane is scheduled for installation in late summer.

Fuel Pump Room and Tower Crane Pad

Fuel Pump Room and Tower Crane Pad

The process of building the foundation for the Fuel Oil Pump Room is underway along the south side of the existing South Addition. Work includes drilling into the existing South Addition foundation walls to install anchors for the new foundation walls, assembly and installation of the reinforcing bars and construction of the foundation wall forms.

Installation of shoring and excavation for the tower crane pad (concrete base) starts this week. This is expected to create noise, but not as much as previous shoring as a different type of shoring system is being used.

Fuel Oil Pump Room Construction Continues

Fuel Oil Pump Room Construction Continues

Construction for the Fuel Oil Pump Room foundation is underway along the south side of the existing South Addition. This work is anticipated to create some noise.

Demolition of the former discharge ramp has resumed and is anticipated to last for three more weeks. This work will include the sound of trucks backing up.

No work is scheduled for January 1, 2, or 3.  

Fuel Oil Pump Room Construction

Fuel Oil Pump Room Construction

The second fuel tank installation is now complete. Excavation for the Fuel Oil Pump Room foundation is underway along the south side of the existing South Addition. Work on this part of the building will include drilling micropiles and pouring foundations, which will begin the week of December 28. This work is anticipated to create minimal noise.

Demolition of the former discharge ramp has resumed and is anticipated to last for three more weeks. This work will include the sound of trucks backing up.

No work is scheduled for December 25, 26, 27 or January 1, 2, and 3.  Crews will be working no later than 3:30 p.m. on Christmas Eve and New Year’s Eve.

Second Fuel Tank Installed

Second Fuel Tank Installed

The second fuel tank has been delivered.  Backfilling and shoring removal for the tank is scheduled to begin on Monday, December 21. This is expected to cause the same level of noise as the shoring of the first tank.

Construction of the Pump House is scheduled to begin next week after the second tank is fully installed. The pump house will be attached to the hospital, behind the area of the first tank. Construction will start with drilling a micropile and building the foundations. 

No work is scheduled for December 25, 26, 27 or January 1, 2, and 3.  Crews will be working no later than 3:30 p.m. on Christmas Eve and New Year’s Eve.