Crews will be on site this Saturday 4/23 using the tower crane to replace a section of the buck hoist (exterior elevator). They will also be spraying the fire proofing and installing framing inside the structure. Work is expected to go from 7 a.m. to 4 p.m.

During the week, the tower crane and buck hoist will continue to be used for construction. Fireproofing and framing will continue on the 6th, 7th, and 8th floors. Crews will also be installing mechanical, electrical, and plumbing lines on all the floors. Swing stage scaffolding is installed on the north side and will be working its way around the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.