Skip to main content

menu

Saturday Work 7/2/22

There will be no work construction work on Sunday 7/3 or Monday 7/4.

Crews will be on site Saturday 7/2 from 7 a.m. to 5 p.m. Work activities will include fire proofing structural members along with installing plumbing inside the building. Crews will also be working on the exterior from the swing stage scaffolding.

During the week, crews will be using the tower crane and buck hoist for activities on site. They will be working on fire proofing structural members, interior/exterior framing, and installing drywall top fill for mechanicals. Mechanical, electrical, and plumbing installation will be taking place in multiple locations within the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday and Sunday Work 6/25 and 6/26

Crews will be on site this Saturday 6/25 from 7 a.m. to 5 p.m. fire proofing structural members and installing plumbing inside the new tower. They will also be installing exterior framing and sheathing. Crews might also be on site this Sunday 6/26 at some point between the hours of 7 a.m. to 5 p.m. to conduct pressure testing on pipes within the new tower.

During the week, activities will include using the buck hoist and tower crane for fire proofing and interior/exterior framing. Drywall top fill will be taking place on the 5th, 6th , and 7th floors and mechanical/plumbing rough ins will continue to be installed throughout the building. Brick installation will also be starting on the fuel oil building on the east corner of the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 6/18

Crews will be on site this Saturday, 6/18 from 7 a.m. to 5 p.m. doing fire proofing and installing plumbing inside the building. Exterior framing and sheathing will also be in the process of being installed on the outside of the building.

During the week, crews will be using the tower crane and buck hoist for a variety of construction related activities between 7 a.m. and 6 p.m. Fire proofing structural members will be occurring on the 4th floor for framing. Interior and exterior framing will be happening on the 5th, 6th, 7th and mechanical penthouse levels. Crew members will be working from boom lifts around the building to install framing and sheathing. Drywall will be installed on the 5th, 6th, and 7th floors. Mechanical, electrical and plumbing roughs in are also being put into multiple locations within the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Weekend Work 6/11 and 6/12

Crews will be on site on Saturday 6/11 from 7 a.m. to 5 p.m. Work will include fire proofing the structure inside the shrink wrapped building, plumbing pressure testing, and exterior framing.

A partial crew will also be on site Sunday 6/12 from 7 a.m. to 2 p.m. conducting plumbing pressure testing inside the shrink wrapped building.

During the week, the tower crane and buck hoist will be used for construction activities. Fire proofing will be happening on the 4th floor. Interior and exterior framing will be happening on the 5th, 6, 7th floors, and the mechanical penthouse. Drywall top fill will be installed on the 5th and 6th floors. Mechanical, electrical, and plumbing rough ins will also be installed in multiple locations within the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Food Trucks on Mt. Vernon Ave.

To offer our employees a bit of food variety, Highland is bringing food trucks to campus on a few select days this summer. On the following dates and times, a food truck will be parked in the Mt. Vernon Ave. cut out near the old oncology entrance:

June 9 – Marty’s Meats 11 a.m. to 1 p.m.

June 15 - Effortlessly Healthy 10:45 a.m.-1:30 p.m.

June 29 - Roc City Sammich 11 a.m.-1:30 p.m.

July 7 - Effortlessly Healthy 10:45 a.m.-1:30 p.m.

We do not anticipate any traffic issues from this event. Neighbors are also welcome to purchase food while the truck is parked near to the hospital.

1 2