Crews will be on site this Saturday 6/25 from 7 a.m. to 5 p.m. fire proofing structural members and installing plumbing inside the new tower. They will also be installing exterior framing and sheathing. Crews might also be on site this Sunday 6/26 at some point between the hours of 7 a.m. to 5 p.m. to conduct pressure testing on pipes within the new tower.
During the week, activities will include using the buck hoist and tower crane for fire proofing and interior/exterior framing. Drywall top fill will be taking place on the 5th, 6th , and 7th floors and mechanical/plumbing rough ins will continue to be installed throughout the building. Brick installation will also be starting on the fuel oil building on the east corner of the building.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.