Skip to main content

menu
Highland Hospital / Facilities / Blog / June 2022 / Saturday Work 6/4

Saturday Work 6/4

Crews will be on site this Saturday, 6/4 from 7 a.m. to 5 p.m. Activities will include fire proofing, framing, layout and plumbing/med gas piping inside the new tower. Outside, crews will be installing exterior framing and sheathing on the north side.

During the week, the tower crane and buck hoist will be used for activities on site and work will be going on from 7 a.m. to 6 p.m. Fire proofing will be taking place on the 4th floor for framing. Interior and exterior framing will be happening on the 5th, 6th, 7th and mechanical penthouse floors. Drywall top fill will be happening on the 5th and 6th floors and mechanical, electrical, and plumbing rough ins will be happening throughout the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 6/2/2022

You may also like

No related posts found.