Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / March 2023

March 2023

Saturday Work 4/1

Saturday Work 4/1

Crews will be on site this Saturday 4/1 from 7 a.m. to 5 p.m. working on installing the fiber cement panels and roofing on the outside of the building, weather depending.

During the week, crews are working on hard wall protection, flooring, and various mechanical/electrical finishes throughout the interior. Outside, work continues on the exterior brick work as well as the roofing and siding.

Crews are anticipating bringing the site work up to grade at the end of April to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Saturday Work 3/25

Saturday Work 3/25

Crews will be on site this Saturday 3/25 from 7 a.m. to 5 p.m. to install siding and roofing (weather depending).

During the week, crews are continuing to work on miscellaneous drywall and mechanical installation activities inside the building. Outside, siding, roofing, and brick work installation continues.

Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Crane Disassembly and Saturday Work

Crane Disassembly and Saturday Work

The tower crane removal is expected to be completed this week with the disassembly crane removed. Site access will be from Mt. Vernon through our current entrance for safety until the crane is removed.  

Crews will be on site this Saturday (3/18) from 7 a.m. to 5 p.m. working on installing fiber cement panels and roofing on the outside, depending on the weather.

During the week, tower crane disassembly should finish up Thursday 3/16 and Friday 3/17. Exterior siding and roofing installation continues. Exterior brick work will start on Monday 3/20.

Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Potential Saturday Work 3/11

Potential Saturday Work 3/11

Mt. Vernon has now re-opened. Access to the site will continue to be from Mt. Vernon for a week or so until the disassembly crane is removed from the site.

Crews will be onsite on Saturday 3/11 from 7 a.m. to 5 p.m. installing fiber cement panels on the west and south sides on the exterior of the building (weather depending).

During the week, all exterior elevation work will be from the swing stage scaffolding or boom lifts. Window, siding, and roofing installation continues.

Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.

Tower Crane Removal Update

Tower Crane Removal Update

Mt. Vernon Ave. is now closed to through traffic with all detours posted. Tower Crane disassembly has begun. Unfortunately, due to the wind speed and the impending snow event on Friday, all tower crane work has been suspended until Monday morning. Constructors will be plowing and salting Mt. Vernon from Rockingham St. to the crane and Doctors Dr./Bellevue Drive to the crane over the weekend.  Safety is our number one priority: for our neighbors, the hospital, and our construction workers.

Once work resumes next week, there will be tractor trailers on Mt. Vernon loading out crane components similar to when the crane was set up. 

Site access will need to vary depending on the disassembly crane location; when the disassembly crane is on Mt. Vernon access will be from the South Avenue side. When the disassembly crane is on site, access will be from Mt. Vernon through our current entrance for safety.