The tower crane removal is expected to be completed this week with the disassembly crane removed. Site access will be from Mt. Vernon through our current entrance for safety until the crane is removed.
Crews will be on site this Saturday (3/18) from 7 a.m. to 5 p.m. working on installing fiber cement panels and roofing on the outside, depending on the weather.
During the week, tower crane disassembly should finish up Thursday 3/16 and Friday 3/17. Exterior siding and roofing installation continues. Exterior brick work will start on Monday 3/20.
Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.