Construction began Monday on the new North retaining wall and the scaffolding has been erected. For the remainder of this week and part of next week, repairs will be done on the existing wall to prepare it for the vertical addition on the wall. The project is on schedule so expect to see the screening wall to start appearing sometime around mid-week. Completion date is still scheduled for mid-November.