Skip to main content

menu
Highland Hospital / Facilities / Blog / October 2021 / No Work Saturday and Friday Parking in Mt. Vernon Cut Out

No Work Saturday and Friday Parking in Mt. Vernon Cut Out

On Friday 10/7, contractors will be removing construction materials from the building in the morning. They will be loading out through the Mt. Vernon Access and to collection containers/vehicles parked within the short term parking area on Mt. Vernon. This activity should be completed by 10 a.m.

Construction Crews will not be working onsite this weekend.

South Building roofing work has been delayed, but is anticipated to start back up in the next week or so once the roofer acquires the Mount Vernon Permit for the crane.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through early October. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start mid-November.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be in full operation erecting the super structure steel. The crane will be running a little later to make up for the loss of morning day light.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Wendy Boyce | 10/7/2021

You may also like

No related posts found.