Skip to main content

menu
Highland Hospital / Facilities / Blog / September 2022

Saturday Work 10/1

Crews will be on site Saturday from 7 a.m. to 5 p.m. working on drywall inside and miscellaneous exterior work from the swing scaffolding outside. Windows will also be installed on the east elevation.

During the week, the tower crane and buck hoist will be used for activities on site. Miscellaneous interior and exterior framing continues on the 5th, 6th, 7th, and mechanical penthouse floors. Full height drywall is being installed on the 6th, 7th, and mechanical penthouse floors. Mechanical, electrical and plumbing roughs ins are being placed in multiple locations within the building. Roofing is being installed on the 7th floor and the mechanical penthouse.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.

Saturday Work 9/24

Crews will be on site this Saturday 9/24 from 7 a.m. to 5 p.m. Interior work will include carpenters putting in drywall/framing and mechanical installations on the upper floors. Outside, crews will be working on hunter panel installation and window installation from the scaffolding.

During the week, the tower crane and buck hoist will be used for various activities on site. Miscellaneous interior and exterior framing will be happening on the 5th, 6th, 7th, and mechanical penthouse floors. Full height drywall is being installed on the 6th, 7th, and mechanical penthouse floors. Painters are laying down the primer and first coat of paint on the floors where the drywall is finished. Mechanical, electrical, and plumbing rough ins continue throughout the building. Brick is being put in on the west elevation then moving toward the north elevation. Roofing is being installed on the 7th floor and the mechanical penthouse.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.

Saturday Work 9/17

Crews will be onsite Saturday 9/17 from 7 a.m. to 5 p.m. Carpenters will be working on drywall and other crews will be working on mechanical piping installations on the upper floors. On the outside of the structure, various work will be happening from the swing stage scaffolding including hunter panel installation, window installation on the east elevations and steel work between the new tower and existing hospital.

During the week, the tower crane and buck hoist will be used for activities on site. Interior and exterior framing continue on the 5th, 6th, 7th, and mechanical penthouse floors. Full height drywall is being installed on the 6th and 7th floors. Painters are working their way through priming and putting the first paint coats where drywall is finished. Mechanical, electrical, and plumbing rough ins continue through the building. Brick is being installed on the west elevation and roofing is being put on the mechanical penthouse.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency. 

Saturday Work 9/10

Crews will be onsite Saturday 9/10 from 7 a.m. to 5 p.m. Carpenters will be working on drywall and miscellaneous framing inside the building while hunter panel installation takes place on the building’s exterior.

During the week, the tower crane and buck hoist will be used for activities onsite. Interior and exterior framing is taking place on the 5th, 6th, 7th, and mechanical penthouse floors. Drywall top fill is being put in on the 6th and 7th floors for mechanicals. Drywall finishing is now taking place on all floors. Mechanical, electrical, and plumbing rough ins continue to be installed throughout the building. Brick is being installed on the new exit corridor.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency. 

No Work Labor Day Weekend

There will be no construction work Saturday, 9/3 through Monday, 9/5 due to the Labor Day holiday.

During the week, crews will be using the tower crane and buck hoist for activities on site. Interior and exterior framing continues on the 5th, 6th, 7th floors and the mechanical penthouse. Drywall top fill is being installed on the 6th , and 7th floor for mechanicals. Full height drywall is being put in on the 6th floor. Mechanical, electrical and plumbing roughs in also continue in multiple locations within the building. Curtain wall window frames are being installed on the east elevation and brick is starting on the new exit corridor.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.