Saturday Work 9/17
Crews will be onsite Saturday 9/17 from 7 a.m. to 5 p.m. Carpenters will be working on drywall and other crews will be working on mechanical piping installations on the upper floors. On the outside of the structure, various work will be happening from the swing stage scaffolding including hunter panel installation, window installation on the east elevations and steel work between the new tower and existing hospital.
During the week, the tower crane and buck hoist will be used for activities on site. Interior and exterior framing continue on the 5th, 6th, 7th, and mechanical penthouse floors. Full height drywall is being installed on the 6th and 7th floors. Painters are working their way through priming and putting the first paint coats where drywall is finished. Mechanical, electrical, and plumbing rough ins continue through the building. Brick is being installed on the west elevation and roofing is being put on the mechanical penthouse.
Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.
Wendy Boyce | 9/15/2022
You may also like
No related posts found.