Exterior Work Resumes Next Week

Exterior Work Resumes Next Week

Site work will resume the week of November 16th starting with excavation and installation of shoring for the fuel tanks. All project related delivery trucks and dumpster deliveries and removals will use the South Access Drive off South Avenue. Normal levels of truck noise can be expected during this time.

Focus Continues on Interior Construction

Focus Continues on Interior Construction

There will be little or no exterior site for the next couple of weeks as demolition and new construction focus on the interior of the building.  Delivery trucks and dumpster deliveries and removals will continue utilizing the South Access Drive off South Avenue with no deliveries before 7 a.m.

Focus on Interior Construction

Focus on Interior Construction

There will be little or no exterior construction for the next couple of weeks as demolition and new construction focus on the interior of the building.  Delivery trucks will continue utilizing the South Access Drive off South Avenue with no deliveries before 7 a.m.

Brick Exterior Removal

Brick Exterior Removal

Crews will begin removing the brick on the east and south sides of the South Addition during the next week. Demolition of the ramp and courtyard area between the South Addition and the South building will also start in the next two weeks. This work could possibly involve a jackhammer, but crews will be trying to saw cut the concrete as much as they can in attempt to avoid using a jackhammer.

There will also be an increase of deliver trucks and dumpster deliveries and removals utilizing the South Access Drive resulting in an increase of truck traffic coming off South Avenue and the sound of back up alarms can be expected. 

Metal Panel Removal Continues

Metal Panel Removal Continues

Crews will continue removing the metal paneling on the outside of the 3rd floor South Addition Mechanical Penthouse.  Windows on the east and south side of the South Addition (1st and 2nd floors) have been covered with plywood for protection, along with the windows in the CafĂ© looking into the courtyard.  This work is anticipated to last another week and will  create normal levels of construction noise.

Following the metal panel removal, the brick on the east and south sides of the South Addition will be removed. There will be some noise and dust created while this work is going on.