Saturday Work 5/14

Saturday Work 5/14

Crews will be on site 7 a.m. to 5 p.m. on Saturday 5/14 continuing work inside the tower. Activities will include fire proofing structural members, framing, layout, plumbing, and duct work. Exterior work will include framing and sheathing on the north and south sides of the building.

During the week, crews will be on site from 7 a.m. to 6 p.m. Both the tower crane and buck hoist will be in use. Contractors will be fire proofing structural members on the 4th floor and the mechanical penthouse. Interior and exterior framing will be installed on the 5th, 6th, 7th floors, and the mechanical penthouse. Drywall top fill will be put in on the 5th and 6th floors. Mechanical, Electrical and Plumbing rough ins are also being installed in multiple locations within the building. Roof demo and curb prep for the new boiler room directly above the 2nd floor south, west corner of the observation unit.

Starting tomorrow through next Friday, crews will also be on site working on an elevator in the main hospital parking garage. This work will be done on weekdays only, from 7 a.m. to 5 p.m. It will involve using a compressor which may create noise on the Rockingham St. side of the hospital.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 5/7

Saturday Work 5/7

Crews will be on site Saturday 5/7 from 7 a.m. to 5 p.m. Work will include exterior framing and sheathing plus fireproofing structural members, framing and plumbing inside the shrink wrapped building.

During the week, the tower crane and buck hoist (temporary exterior elevator) will be used for construction activities onsite. Crews will be fireproofing on the 4th floor and in the mechanical penthouse. They will also be installing interior and exterior framing on the 5th, 6th, 7th floors, and the mechanical penthouse using the swing stage scaffolding and drywall top fill on the 5th and 6th floor for mechanicals. Roof demo and curb prep will be taking place for the new boiler room directly above the 2nd floor south, west corner of the Observation Unit.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 4/30

Saturday Work 4/30

Crews will be on site this Saturday 4/30 using fire proofing spray and installing framing inside the wrapped building as well as installing exterior framing and sheathing on the north and east elevations from 7 a.m. to 4 p.m.

During the week, the tower crane and buck hoist (temporary exterior elevator) will be conducting operations on the outside of the tower. Crews will also be fire proofing on the 4th and 8th floors. Interior and exterior framing will be going in on the 5th, 6th, 7th, and 8th floors and drywall top fill will be installed on the 5th and 6th floors. Roof demolition and curb preparation will be taking part on the roof of the 2nd floor in the southwest corner of the Observation Unit.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 4/23

Saturday Work 4/23

Crews will be on site this Saturday 4/23 using the tower crane to replace a section of the buck hoist (exterior elevator). They will also be spraying the fire proofing and installing framing inside the structure. Work is expected to go from 7 a.m. to 4 p.m.

During the week, the tower crane and buck hoist will continue to be used for construction. Fireproofing and framing will continue on the 6th, 7th, and 8th floors. Crews will also be installing mechanical, electrical, and plumbing lines on all the floors. Swing stage scaffolding is installed on the north side and will be working its way around the building.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 4/16

Saturday Work 4/16

Crews will be on site Saturday 4/16 from 7 a.m. to 4 p.m. fire proofing the inside of the shrink wrapped building. They will also be building framing and layout as well as installing some structural steel.

During the week, the tower crane will be in use for various activities on site. Crews will also be using the buck hoist (temporary exterior elevator) and fireproofing the inside of the 6th, 7th, and 8th floors. Crews will also be putting together the interior and exterior framing for the 5th, 6th, 7th, and 8th floors. Swing stage scaffolding is installed on the north side, with the east elevation operational. Roof demo and roof curb prep continues for the new boiler room directly above the 2nd floor south west corner of the observation unit.

The 4th floor concrete deck pour is tentatively scheduled for Thursday  April 21st  starting at 7 a.m. Concrete finishing has the potential to run late into the night but will not go past the City noise ordinance of 10 p.m.

Please keep in mind the concrete pour tentatively scheduled for next week will have the concrete pump on the south side of the new tower (engine running the during the entire pour), 2 concrete trucks rotating in and out at the concrete pump (engines running), and 1 concrete truck washing out (engine running). Crews will be in constant communication with the batch plant adjusting truck spacing depending on how the pour is progressing.

A flag person will be stationed at the South Avenue entrance to help back in the concrete trucks and help with traffic flow.