No Work This Weekend Saturday 3/12 or Sunday 3/13
There will be no work on site this weekend.
During the week, the tower crane will be operating with roofing and other activities on site. Stair risers are being filled with concrete for easier access and are tentatively scheduled for Friday, March 11th and Tuesday, March 15th starting at 7 a.m. Concrete finishing has the potential to run late into the night, but will be finished before the City of Rochester noise ordinance of 10 p.m. An temporary extra deck called a Preston deck will be installed on the side of the new tower this week using the tower crane. Layout is being installed on the 5th, 6th and 7th floor with top track. Interior and exterior framing is being installed on the 1st and 2nd floors. Swing stage scaffolding will start to be installed next week on the east side, working their way around to the north side.
No Work This Weekend
There will be no outdoor work on site this weekend Saturday 3/5 or Sunday 3/6.
During the week, crews will be using the crane to install roofing. The 8th floor concrete slab installation is tentatively scheduled for Friday, March 4 starting at 7 a.m. Stair L risers are being filled with concrete for easier access is tentatively scheduled for Thursday, March 10 starting at 7 a.m. All concrete finishing has the potential to run late into the night but will be finished before the City of Rochester noise ordinance begins at 10 p.m. Layout will begin on the 5th, 6th and 7th floors and top track. Fire Proofing will take place on the 4th, 5th and 6th floors before framing is installed. Interior and exterior framing will begin on the 1st and 2nd floors.
Work on Saturday 2/26/22
Crews will be on site Saturday 2/26 from 7 a.m. to 3 p.m. installing fire proofing in the new tower.
During the week, the tower crane will be in operation with roofing and other activities on site. The 7th floor concrete slab installation is tentatively scheduled for Monday, February 28th starting at 7 a.m. Stair risers are being filled with concrete for easier access is tentatively scheduled for Wednesday, March 2nd starting at 7 a.m. The 8th floor concrete slab installation is tentatively scheduled for Friday, March 4th starting at 7 a.m. All concrete finishing has the potential to run late into the night, but will not go past the City of Rochester noise ordinance of 10 p.m.
No Work Saturday 2/19
There is no work scheduled this weekend.
During the week, the tower crane will be in operation installing roofing. The 7th floor concrete slab installation is tentatively scheduled for Friday, February 25th starting at 7 a.m. Concrete finishing has the potential to run late into the night, but will not run past the City of Rochester noise ordinance of 10 p.m. Crews will also be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, embedments, and rebar. The stair risers are being filled with concrete for easier access from floor to floor. New tower 7th and 8th floor temporary roofing / vapor barrier is also being installed (weather dependent activity). Interior and exterior framing has started on the 1st and 2nd floors.
No Work Saturday 2/12 or Sunday 2/13
There will be no construction work on site this weekend Saturday 2/12 or Sunday 2/13.
During the week, the tower crane will be in operation with the roofing and other activities on site. The 6th floor concrete slab installation is tentatively scheduled for Tuesday, February 15th starting at 7 a.m. Concrete finishing does have the potential to run late into the night but will not go past 10 p.m. per the City of Rochester noise ordinance. Mechanical hangers are being installed on the 7th and 8th floors new decks for future installation of the mechanical piping. Crews are preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, embedments, and rebar. The stair risers are also being filled with concrete for easier access from floor to floor. Crews are installing temporary roofing/vapor barrier on the 7th floor (weather dependent activity). Interior and exterior framing has started on the 1st and 2nd floors.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.