Saturday Work 2/5

Depending on the amount of snow received by then and weather conditions on that day, crews could potentially be on site this Saturday 2/5 from 7 a.m. to 3:30 p.m. to remove snow from the 7th and 8th floor deck. The crane may also be in operation during this time. Building wrapping may be occurring depending on the weather.

No Work This Weekend 1/29 and 1/30

There will be no exterior construction work this weekend at the site.

During the week, the tower crane will be in operation building the super structure steel and steel workers will be detailing the decking the 8th floor. The fifth floor concrete slab installation is tentatively scheduled for Friday, January 28th starting at 7 a.m. Concrete finishing has the potential to run late into the night, the building wrap should isolate us from any impact to neighbors and patients. Mechanical hangers will be installed on the 7th and 8th floors new decks for future installation of the mechanical piping. The stair risers are being filled with concrete for easier access from floor to floor. Temporary building enclosure is being installed using ZAP wrap on the 6th and 7th floors. New tower 7th floor temporary roofing / vapor barrier will be installed (weather dependent activity).

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

No Work Saturday 1/22

There will be no construction work this weekend.

During the week, the tower crane will be in operation with the super structure steel as the steel workers will be detailing the decking the 8th floor. The fifth floor concrete slab installation is tentatively scheduled for Friday, January 28th starting at 7 a.m.  Concrete finishing has the potential to run late into the night, but the building wrap should keep this activity from any impact to neighbors and patients. Mechanical hangers are being installed on the 6th, 7th and 8th floors new decks for future installation of the mechanical piping. Crews are also preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, embedments, and rebar. The stair risers are being filled with concrete for easier access from floor to floor. Temporary building enclosure is being installed utilizing ZAP wrap on the 5th and 6th floors. The new tower 7th floor temporary roofing / vapor barrier will also be put in place this week (weather depending).

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 1/15

Crews will be on site Saturday 1/15 working on the structural steel and detailing decking on the upper floors from 7 a.m. to 4 p.m. (weather dependent). Concrete workers will also be on site covering the 2nd floor newly poured slab with concrete blankets.

During the week, the tower crane will be in operation building super structure steel as the steel workers detail decking on the upper levels. Crews will also be pouring the second floor concrete slab on Friday 1/14 starting at 7 a.m. and pouring the third floor concrete slab on Tuesday 1/18 (weather dependent). Concrete finishing has the potential to run later into the day, but the building wrap should isolate any potential impacts to the neighborhood. Mechanical hangers are being put in on the 6th, 7th and 8th floors new decks for future installation of the mechanical piping.  The stair risers are being filled with concrete for easier access from floor to floor. Temporary building enclosure is happening using ZAP wrap. New tower 7th floor temporary roofing will be installed starting the week of January 17th (weather dependent).

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 1/6

Crews will be on site this Saturday 1/6 performing structural steel erection and detailing decking from 7 a.m. to 4 p.m. (depending on the weather).

During the week, the tower crane will be in operation with the super structure steel as steel workers detail decking. Mechanical hangers will be installed on the 2nd,  3rd, 4th, 5th and 6th floors new decks for future installation of mechanical piping. They will also be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves and embedments. The stair risers are being filled with concrete for easier access from floor to floor and crews are working to install temporary building enclosures using ZAP wrap.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.