Construction on Saturday 7/24
Crews will be onsite Saturday, July 24 from 7 a.m. to 4 p.m. stripping foundation forms, which is similar to the work that was done last Saturday. Tower crane construction may also be occurring on Saturday.
Deep foundation, pile cap and grade beam installation is ongoing and will continue for approximately three more weeks. Excavation and grading work are happening at the same time as the deep foundation installations.
The Mt. Vernon Rd. closure between Rockingham and Bellevue will begin on Friday, 7/23 and last for about a week. This temporary road closure is necessary so materials and a small crane can be staged in the area to build a large crane on the hospital campus, which will be used to erect the patient tower.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Work on Saturday, 7/17
Crews will be onsite Saturday, July 17 from 7 a.m. to 4 p.m. stripping foundation forms, which is similar to the work that has occurred during this week.
Deep foundation, pile cap and grade beam installation is ongoing and will continue for approximately 7 weeks. Excavation and grading work are happening at the same time as the deep foundation installations.
Mt. Vernon Avenue will be closed to public traffic between Rockingham Street and Bellevue Drive for one week starting Friday, July 23. This temporary road closure is necessary so materials and a small crane can be staged in the area to build a large crane on the hospital campus, which will be used to erect the patient tower. A flagger will be on hand to direct traffic and help neighbors access their driveways during the temporary road closure. Letters have been sent to residences between Rockingham and Bellevue to notify them in advance of the temporary road closure.
Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start in late July, early August. Fill material will be placed in “lifts” and compacted until the final grade height is reached.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Saturday Work 7/10
Crews will be doing foundation drilling work on Saturday, July 10 from 7 a.m. to 5 p.m. in the temporary canyon area between the current south wing and the south addition.
Deep foundation, pile cap and grade beam installation is ongoing and will continue for approximately 7 weeks. Excavation and grading work are happening at the same time as the deep foundation installations.
South Building roofing work has been delayed but will continue shortly.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
No Work July 4th Weekend
There will be no construction work this weekend or on Monday, July 5.
Deep foundation, pile cap and grade beam installation will continue on the project for approximately 9 weeks. Excavation and grading work will happen at the same time as the deep foundation installations.
South Building roofing work has resumed and will continue for the next few weeks.
Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Saturday Construction 6/26
Crews will be on site working on exterior foundation work this Saturday 6/26 between the hours of 7 a.m. and 5 p.m. as part of the Patient Tower Construction Project. Deep foundation, pile cap and grade beam installation will continue on the project for approximately 9 weeks. Excavation and grading work will happen at the same time as the deep foundation installations.
South Building roofing work is temporarily on hold.
Crews will also be working on Saturday 6/26 on the retaining wall along South Ave. outside the Professional Office Building. That work is expected to take place between 8 a.m. and 4 p.m. and will continue Monday through Friday of next week. The sidewalk on South Ave. between the Highland sign and the fire hydrant will be closed for safety reasons for the duration of the project. The road lane next to the project will also be partially closed at times and a flagger will be on hand for traffic as necessary.
Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.