Skip to main content

menu

Saturday Work 12/17

Crews will be onsite this Saturday, 12/17 from 7 a.m. to 5 p.m. installing windows and siding on various sides of the building, weather permitting.

During the week, crews will be working inside the building to finish drywall, painting, and various mechanicals. Outside, the tower crane will be in use, moving materials from floor to floor. Scaffolding and boom lifts will be in use for window and siding installation. Roofing continues on the 7th floor and various bump outs. Crews will also be working on installing a new manhole and storm piping.

Saturday Work 12/10

Crews will be onsite this Saturday from 7 a.m. to 5 p.m. installing windows and siding on various elevations, weather permitting.

During the week, crews will be working on drywall and various mechanical projects inside the building. Outside, the tower crane will be in use moving materials from the ground to various floors of the building. Window and siding installation continues on different sides of the building. Roofing continues on top of the 7th floor.

Saturday Work 12/3

Crews will be onsite this Saturday from 7 a.m. to 5 p.m. installing windows and siding on various elevations, weather permitting.

During the week, crews will be working on drywall and various mechanical projects inside the building. Outside, the tower crane will be in use moving materials from the ground to various floors of the building. Window and siding installation continues on different sides of the building. Roofing continues on top of the 7th floor.

The buck hoist foundation will be demolished this week starting on Monday and should be finished by Friday. This work has the potential to produce noise and vibration. In order to minimize impact, crews will be saw cutting the foundation into small sections that can be placed into a dumpster, a different approach than previous foundation demolitions. Vibration monitoring will be in place for these activities.

In the coming weeks, crews will be working to raise the pavement area next to the new tower to be the same level as Mt. Vernon Ave. This activity is anticipated to generate some minor vibration, and more details will be sent out via this blog as we get closer to this work occurring.

Saturday Work 11/19

Crews will be on site this Saturday 11/19 from 7 a.m. to 5 p.m. installing windows and siding, weather permitting.

During the week, crews will be using the tower crane and buck hoist for various activities on site. Inside, painting, drywall finishing, and various mechanical installations continue on multiple floors. Outside, crews will be installing windows and siding on various sides of the building and continuing to put in the roof on top of the 7th floor.

These activities are expected to produce typical levels of construction noise but no vibrations.

There will be no blog post sent out next week and no work on site Thursday, 11/24, because of the Thanksgiving holiday. Crews will be on site next Friday 11/25 and Saturday 11/26 from 7 a.m. to 5 p.m. painting inside the building and installing windows on various sides.

In early December, crews will be working to raise the pavement area next to the new tower to be the same level as Mt. Vernon Ave. This activity is anticipated to generate some minor vibration, and more details will be sent out via this blog as we get closer to this work occurring.

Saturday Work 11/12/22

Crews will be onsite on Saturday 11/12 from 7 a.m. to 5 p.m. installing windows and siding on various sides of the building. They will also be installing roofing.

During the week, crews will be installing drywall, painting, and finishing up various mechanicals on multiple floors inside the building. Outside, the tower crane and buck hoist will be used for activities on site. Crews will be installing windows and siding on various sides of the building and roofing on top of the mechanical penthouse.

These activities are expected to produce typical levels of construction noise but no vibrations.

Later in November or early in December, crews will be working to raise the pavement area next to the new tower to be the same level as Mt. Vernon Ave. This activity is anticipated to generate some minor vibration, and more details will be sent out via this blog as we get closer to this work occurring.

1 2 3 4 5 6 7 8 9 10 ... Last